Residents across the North West province will see some relief as Eskom announced a reduction in loadshedding to Stage 4 starting from 00:30 on Monday, 24 February 2025, until further notice.
This follows the successful recovery of several power generation units after multiple breakdowns over the weekend, including:
• All five units at Majuba
• Two units at Camden
• One unit at Medupi
According to Eskom, eight out of ten units that had tripped this past weekend have returned to service. The issues causing these trips were described as purely technical in nature, linked to electrical and control system faults in auxiliary components at power stations.
Advertisement:

Planned Maintenance & Updates
Eskom stated that emergency reserves are being replenished, and planned maintenance currently accounts for 7,706MW of unavailable capacity. The power utility will provide another update on Monday afternoon regarding further developments in the national power grid.
Loadshedding Schedules for Key Areas in Dr. RSM District
Here’s what residents in various areas can expect for Monday:
Taung
• 00:00 – 00:30 – Stage 6
• 04:00 – 06:30 – Stage 4
• 12:00 – 14:30 – Stage 4
• 20:00 – 22:30 – Stage 4
Stella
• 00:30 – 02:30 – Stage 4
• 08:00 – 10:30 – Stage 4
• 16:00 – 18:30 – Stage 4
Morokweng
• 00:00 – 00:30 – Stage 6
• 06:00 – 08:30 – Stage 4
• 14:00 – 16:30 – Stage 4
• 22:00 – 00:00 – Stage 4
Ganyesa
• 02:00 – 04:30 – Stage 4
• 10:00 – 12:30 – Stage 4
• 18:00 – 20:30 – Stage 4
Huhudi
• 00:30 – 02:30 – Stage 4
• 08:00 – 10:30 – Stage 4
• 16:00 – 18:30 – Stage 4
What This Means for Residents
The reduction in loadshedding levels is a positive sign that Eskom is stabilizing supply after a weekend of disruptions. However, residents are advised to continue using electricity sparingly and to keep updated on further announcements.
For real-time updates, residents can monitor Eskom’s social media pages or visit the official website.
Stay prepared, and let’s manage our electricity use wisely!